Fleet Street, London
500mm HDPE Slip Lining Project in Fleet Street, London
The length of the project was 800m and the duration was 8 weeks
Chalk Farm, London
500mm HDPE Slip Lining Project in Chalk Farm, London
The length of the project was 1.5km and the duration was 12 weeks
Jacksonville, USA
900 mm HDPE Tight Fit Lining Project, 6 km in length.
The project was carried out in Jacksonville, USA over a 20-week period
M25 Junction 10 UK
M25, UK Junction 10 Widening Scheme Diversionary Works.
Installation of 630mm medium pressure gas main including all Butt fusion / Electro fusion.
The project included a 12m deep shaft and took 6 months to complete.